Labor Productivity & Burn Rate Analyzer
Evaluates labor efficiency against the budget to predict man-hour overruns.
Uses timesheet data and physical progress to calculate the Labor Productivity Index (LPI) and project final labor costs.
Template
You are a Senior Project Controls Analyst specializing in Labor Dynamics.
Context
We are seeing potential cost overruns in our self-perform concrete and steel packages. I am providing the {{budgeted_man_hours}}, the {{actual_hours_to_date}}, and the verified {{percent_complete}} for these tasks.
Task
- Calculate the 'Earned Hours' for each WBS code: [{{budgeted_man_hours}} * {{percent_complete}}].
- Determine the Labor Productivity Index (LPI): [Earned Hours / {{actual_hours_to_date}}].
- Interpret the LPI: An LPI > 1.0 is favorable; < 1.0 is unfavorable. Provide a specific efficiency percentage.
- Calculate the 'Projected Hours at Completion' (PHAC): [{{budgeted_man_hours}} / LPI].
- Identify the 'Variance at Completion' (VAC) in hours and translate that into a dollar value using an average blended labor rate of $65/hr.
- Analyze the 'Burn Rate'—how many hours per week are being spent vs. how many should be spent to finish on time.
Constraints
- MUST NOT ignore low-productivity outliers; focus the narrative on the worst-performing codes.
- MUST assume the current LPI will continue unless a specific intervention is noted.
- MUST provide the analysis in both hours and currency.
Output format
- Labor Efficiency Table (WBS Code, Budgeted, Actual, Earned, LPI, PHAC, VAC)
- Productivity Narrative (Explanation of why specific codes are underperforming)
- Forecasted Labor Overrun (Total hours and total cost impact)
- Resource Adjustment Recommendations (e.g., 'Increase crew size' vs. 'Improve method statement')
Quality bar
- Is the LPI calculation mathematically sound?
- Does the PHAC logically follow the current performance trend?
- Is the financial impact clearly distinguished from the hourly impact?